Wednesday, September 1, 2010
FINAL EXAMINATION PART 3 - 1/2 HOUR PAPER - 26 May 2010
Please below the questions from the latest examination short paper - Wednesday 26 May 2010
Please feel free to comment the answers.
MANAGEMENT OF CONSTRUCTION
3.a Briefly describe the difference between Management Contracting and Construction Management.
answer: the distinction between MC and CM lies in the degree to which the client accept to enter into a direct contractual relationship with the work/trade contractors.
In MC contractual relationship is through the manager contractor.
In CM the client appoints directly the work contractors.
3.b Your project has reached Practical Completion under JCT SBC05 contract: what documentation will you issue what are the consequences?
answer: the Architect/Contract Administrator issues a Certificate of Practical Completion. It's the start of Liability Period, half of the retention fee is released to the contractor.
3c. What is a Performance Bond?
answer: a Performance Bond is a Contractual Arrangement between the Employer and a 3rd Party called Guarantor. Under this agreement the guarantor will pay a certain amount of money to the employer if the Contractor won't be able to perform his obligation under the terms of the building contract.
Paolo Fang - 21/08/10
3d. Describe the difference between patent and latent defects.
answer: a Patent Defect is a defect discovered during the reasonable exercise of due diligence by the professional while the Latent Defect is a concealed defect in the workmanship or design not immediately visible.
3e. What are LADs, on what are they based and how are they deducted?
answer: liquidate damages refer to a reasonable amount of money due to the employer by the contractor because of late completion. LADs are stated in the contract particulars and the payment is due after the issue of Non-Completion Certificate
Paolo Fang - 01/09/10
PRACTICE MANAGEMENT AND BUSINESS ADMINISTRATION
4a. You are considering going into partnership with a colleague. List the issues you consider should be incorporated into an agreement.
answer: amount of capital provided by each partner, duties of partner, portions of profit or losses between each partner
4b. What is a RIDDOR?
answer: Reporting of Injuries, Diseases and Dangerous Occurrences Regulations is a legal duty for the employer to report an accident to the HSE.
4c. The HGCR Act 1996 grants three important rights in relation to a party's entitlement to payment- list them
answer: all construction contracts have to contain certain payment provisions such as: (compulsory payments by installments(?)), Paying party must specify to the payee the amount of each payment and the basis on which it has been calculated, withhold payment by the employer must be made under written notice at least 7 days before the due payment date and ground of such withhold has to be specified.
4f. Your practice has insisted that you increase your working hours in the view of their increased work load.You are reluctant to do so as you are preparing for your Part 3 Examination. What are your rights and under what legislation?
answer: Under the EC working time Directive 93/104 the Maximum Weekly working time is 48 hours. The employee is entitled to receive up to 4 weeks annual paid leave.
Paolo Fang - 23/08/10
THE CONTEXT OF PRACTICE
1a. The duties of the ARB are contained within the 1997 Architects Act which covers five main areas: list four of these.
answer: updating Architect Register, investigate complain about architect's conduct/competence, set standard for education, decide qualification needed to become an architect.
1b. What is the role of an RIBA Client Design Advisor?
answer: the RIBA CDA is an independent professional advisor with experience in construction, specially trained to maximize the quality and the value of construction project.
1c. What are the three principles of the RIBA Code of Conduct?
answer:integrity, competence, relationship
1d. What is the role of the Environmental Agency?
answer: EA is a no-departmental public body with the aim to protect and improve the environment and to promote sustainable developments.
1e. Under the Public Sector Directive and Public Contracts Regulations 2006, contracts have to be advertised throughout the EU, however there are three exceptions to these rules- what are they?
answer: 1.contract water, energy, transport and postal service, 2.telecommunication, 3. secret or security measures required
1f. List the primary planning legislation including that related to listed building/conservation areas.
answer: Town and Country Planning Act 1990 - Planning (Listed Building and Conservation Area) Act 1990 - Building Act 1984 - Fire Precaution Act 1971
Paolo Fang - 23/08/10
THE MANAGEMENT OF ARCHITECTURE
2a. What is a BREEAM and what dose it apply?
answer: Environmental Assessed Method for buildings. It sets the standard for best practice in sustainable design and it's used to describe a building environmental performance.
2b. Under the Party Wall Act 1996, what is the role of the 3rd surveyor and at what stage is he/she appointed ?
answer: the third surveyor is appointed when the client's surveyor and the adjoining property's surveyor don't reach an agreement. His role is to 'settle the dispute'.
2c. What means are available to a Local Planning Authority to prevent the continuation of a development which is in breach of planning control?
answer: the LPA can issue an Enforcement Notice to stop the development which is in breach of planning control.
Paolo Fang - 02/09/10
2d. Give three examples of easement.
answer: right of light, right of way, right of support.
2e. What is a section 106 Agreement?
answer: S 106 of the TCPA 1990 is an agreement between the developer and the LPA. The developer provide infrastructures to mitigate the impact of the proposed development to the local community. eg. Westfield Ltd has provided a new library with the new Shopping Centre in Fulham and Hammersmith Borough Council.
2f. Wha is an SPV? Also briefly describe its function.
answer: Special Purpose Vehicle is a legal entity created to fulfill specific objective. The main financial reason behind its creation is to reduce the risk.
http://www.alway-associates.co.uk/legal-update/article.asp?id=68
Paolo Fang - 02/09/10
Sunday, June 20, 2010
CASE SCENARIO PAPER 1
General Scenario
You are a fully qualified and registered architect and together with two similarly qualified University friends you formed a practice six years ago.
The practice is a limited liability company with yourself and your two friends as Directors. The Company employs a total of ten people including a part time office manager/bookkeeper. You lease office space in Hoxton which is now too small for your needs.
The practice has been very busy but due to the current financial situation two major projects have been delayed and you are concerned about the need to acquire new work if the present workforce is to be maintained. The practice has just received an enquiry from a Developer for involvement on a large block of flats, you are proceeding apace with the design for a major office development and are completing a number of other projects on site including a four storey office block and a Sports Hall.
The scenario for each question gives a brief description of a specific situation; the candidate is free to state their own assumption of what took place prior to this event.
__________________________________________________________________________
Section A – Practice Management and Business Administration
Scenario for Question 1
Question 1 What action will you take in respect of ‘time sheets’ and explain how the information contained on time sheets can be of use and value to the practice?
I would arrange an in-office meeting with all the staff and try to explain the importance of completing properly the timesheet. I would let them know that the clients could be for some project charged at fee time basis and if it the case the timesheet would be fundamental to calculate such fees. I would instruct the administrative staff to collect every Friday evening the timesheet and prepare a spreadsheet with the breakdown of the hours spent by every member of staff on every project.
What will you do about the forthcoming audit?
Scenario for Question 2 The practice has recently failed to get onto a short list because it did not meet the requirement to be QA registered. You have been asked by your fellow Directors to prepare a paper on what is involved in achieving and maintaining registration and the impact it will have on the day to day life of the office.
Question 2 Prepare a paper for consideration at the next Board Meeting setting out your thoughts and your recommendations for action.
Section B – The Management of Architecture
Scenario for Question 3 The scaffolding has just been struck on the four storey 3,000m2 office building contract revealing the new brick façade. You are concerned about the widespread inconsistency of the colour of the mortar joints. You arrange to have a sample test taken in one of the worst areas and the results indicate that the mortar is of an incorrect mix resulting in the colour variation; it contains insufficient cement and an unknown additive. The report advises that the structural strength of the wall may be compromised.
You advise the contractor of the results and ask for an explanation. The contractor states that this area of mortar is a one-off error and that as the Interim Certificates had included for this work this means that you, as the Contract Administrator, had accepted that the quality and workmanship were in accordance with the contract (‘SBC05.With Quantities’)
Question 3 Write to the Contractor responding to his comments and state the action you intend to take, quoting the relevant clauses of the contract in support of your action.
Dear Sir,
RE: Instruction for testing under clause 3.17
Following the site inspection of (date) defective works have been discover in respect of
type of mortar used. Under the contract provision (SBC05), clause 3.18.4 further test are
needed in order to ascertain the extent of defective works. Under clause 3.18.4 all the tests
are at Contractor's cost, regardless of the outcome of the test.
If the tests prove that the work to be satisfactory the Contractor is entitled to request an
extension of time if the test has delayed the progress of the Works.
_______________________________________________________________________
Scenario for Question 4 The Directors consider that they are aware of the importance of continuing professional development and demonstrate this by providing occasional lunchtime seminars from manufacturers. However a member of staff has complained that this provision is inadequate, he adds that he has heard from friends that the RIBA are carrying out inspections of CPD records and is concerned that the office is not meeting their obligations.
Question 4 Prepare a note to be sent out to all members of staff advising them of the RIBA CPD obligations and set out what future steps the office intends to take in respect of this matter.
Section C – The Management of Construction
Scenario for Question 5 A client you have worked with in the past has recently acquired a site with an existing large disused concrete framed chemical laboratory building. He proposes to demolish the building, clear the site and erect a block of fifty, 120m2, high quality, up-market flats with underground car parking. The development does not present any planning problems and it can be assumed that these matters will be dealt with within the minimum time scale. He wants to start work on site as soon as possible and seeks your advice on the best way to achieve an early start, possible forms of contract and information on the procurement and tendering procedure.
Question 5 Comment on particular issues that may arise in the development of this site and the way they could be dealt with to allow an early start on the construction of the new building.
Set out the principles of tendering, the criteria for the selection of tenderers and typical procedures for the process of obtaining tenders.
Scenario for Question 6 There is a long lasting contractual dispute on the Sports Hall contract between the Employer and the Contractor, you have made every attempt to try and settle the matter but both parties are adamant in their views. Determined to resolve the issue the Contractor has now exercised his right under the SBC05 Contract to refer the dispute to adjudication. The contract particulars state that the President of the RIBA shall nominate the adjudicator.
The Employer is very concerned about the situation, he has asked you to explain what is involved and if the Adjudicator’s decision is final and binding.
Question 6 Write a formal letter to the client explaining the role and responsibilities of the adjudicator and the procedure and timetable to be followed by both parties to the dispute. Also respond to the specific question on the status of the Adjudicator’s decision.
Section D – The Context for Practice
Scenario for Question 7 Three months ago you were appointed to lead the design team for a new office block on a very tight programme and you are pushing ahead as quickly as possible with the design and preparation of the planning application.
On your appointment you had written to the client advising them of their responsibilities under the CDM Regulations 2007 but you have heard nothing from them on this matter.
Question 7 What action will you take? Describe your own responsibilities under CDM as a member of the design team and the procedures that need to be followed throughout the design stage, construction and completion of the project.
Scenario for Question 8 In March 2008 a new client appointed the practice to design a new house with a construction budget cost of £750,000. He has acquired a spectacular but sensitive agricultural site on the outskirts of an old village and wants a radical 21st century design. As the design stage progressed, in consultation with the client, meetings were held with the planning officer and also with the village amenity association who expressed their opposition to the application. Prior to the submission of the planning application you understood from the planning department that the officer’s report would be recommending that consent be given to the application.
In the event the Planning Committee refused consent and you have just received notice of their decision stating the reasons for refusal which include refusal of Change of Use and the inappropriate design. You have conveyed the news to the client who is very upset but is determined to proceed with the project and has asked you what options are open to him and what are the implications of each alternative in respect of risk, cost and time.
Question 8 Write a formal letter to the client explaining what options are available setting out the pros and cons of each in respect of risk, cost and time.
Wednesday, May 5, 2010
THE CONTEXT FOR PRACTICE
a) Briefly describe the role of Design Review Panels?
Design Review Panels are experts members of CABE who can support good design through the planning process, particularly for those schemes in England that will have a significant impact on their environment.
http://www.cabe.org.uk/
b) What are the advantages of trading as a Limited Liability Partnership?
The main advantage of trading as LLP is that the members are able to limit their liability if something goes wrong with the business (compared with the traditional partnership where the partners may be more expose to greater personal liability)
c) What the following acronyms stand for?
- CABE stands for Commission for Architecture and the Building Environment.
- CIC stands for Construction Industry Council.
- AABC stands for Register of Architects accredited in building conservation.
d) You have been involved in protracted negotiations with the planning department on a specific project. A firm of local architect has contacted your client offering their service - what action can you take?
You can refer to the ARB Code of Conducte 2010 - Standard 3.1 "You are expected to promote your professional services in a truthful and responsible manner."
http://www.arb.org.uk/professional_standards/regulating_architects/architects_code_2010/code.php#s3
e) As qualified Architect you are required to undertake Continuing Professional Development -outiline the RIBA annual requirements.
- You must do at least 35 hours of CPD each year.
- Of these, 19.5 hours must be gained from our RIBA CPD Core Curriculum syllabus, including health and safety.
- You can get the other 15.5 hours from relevant subjects of your choice.
f) Briefly describe the key resonsabilities of the designer under CDM Regulations.
- Eliminate hazards and reduce risks during design.
- Provide information about remaining risks.
- Check client is aware of duties and CDM co-ordinator has been appointed.
- Provide any information needed for the health and safety file.